spacer.gif (883 bytes)
FAQs for AWEA's Grid Code Filing
Text of the Filing (PDF Version)

Revision 4 July 1, 2005

What is the “Grid Code”?
AWEA has proposed an interconnection standard and set of procedures for wind facilities of 20 MW and larger. This is the “Grid Code Filing.” AWEA filed this at the Federal Energy Regulatory Commission (the Commission) on May 20, 2004, to be used by regulated transmission owners/operators for future requests for interconnection of wind farms. This proposal is a summary of AWEA’s effort to describe a set of reliability and utility system issues related to wind generation. That initial effort was followed by an "Electrical Guide to Utility-Scale Wind Turbines" or “Grid Code” that serves as a reference for utilities, transmission owners/operators, and the industry. The Guide is available here.

How does the Grid Code Filing fit into FERC Order 2003-A?
The Grid Code is a response to footnote 85 on page 86 and Attachment G of Order 2003-A, where the Commission left open the details of wind interconnection for future review. These two sections of Order 2003-A create an affirmative duty for wind energy interests to participate in the interconnection and power supply process. The Commission is using the Grid Code Filing to start a docket (RM02-1-005) to determine standard wind farm interconnection requirements for Open Access Transmission Tariffs (OATT) regulated by FERC.

How was the Grid Code created?
AWEA coordinated a committee of wind industry and utility representatives (manufacturers, owners, developers, utilities, constructors) that worked for 6 months to create the draft Grid Code. This committee continues to aid AWEA in completing the white paper and communicating the importance of a standard to the utility and regulatory communities.

What impact does the Grid Code Filing have on wind projects in development?
This proposal, if accepted, will apply to new wind generation projects of 20 MW and larger that have not signed an Interconnection Agreement with the transmission owner or operator (Transmission Provider) when the new OATT language becomes effective. The Commission’s Large Generator Interconnection Order 2003-A establishes the threshold of 20 MW. An estimate of the timetable and a list of engineering issues are below.

What is the timetable for the Grid Code Filing to become effective?
AWEA’s filing is part of a process that may be completed this year. When the Commission issues a decision in docket RM02-1-005, a notice will be issued with a deadline of 30-45 days for utility and system operators to respond. Individual transmission owners and operators will be required to file with the Commission the approved version of the Grid Code as part of their OATT Interconnection Procedures and Interconnection Agreement. The physical standards are proposed to become effective for interconnection requests submitted to a Transmission Provider on the latter of:

1) final approval of a Transmission Provider’s interconnection tariff incorporating these standards; or

2) six (6) months following the Commission’s final order.

The procedural changes are requested immediately following the Commission’s final order.

What technical issues are addressed by the Grid Code Filing?
The proposal sets out requirements that are to be applied only if the interconnecting utility determines they are needed. The engineering requirements address: low voltage ride-through, telecommunications capabilities, power factor within the range of up to 0.95 leading and up to 0.95 lagging, and the update and use of turbine and system models for interconnection design. (See full text)

What will developers do differently once the proposed Grid Code Filing is adopted by FERC?

If adopted as proposed by AWEA, the Grid Code Filing provides developers with an improved process for interconnection, and a uniform set of requirements known to all equipment vendors.

The proposed change in the interconnection study process provides the option for the developer to study the initial feasibility of interconnection designs. This “self-study” of feasibility means that the wind generator will be permitted to submit the Interconnection Application without the provision of the load flow parameter data, but otherwise continue to pay the $10K deposit, enter the interconnection queue, have the scoping meeting with the Transmission Provider, and receive from the Transmission Provider the base case grid data. The wind generator will then be permitted to self-study the feasibility of interconnection and present the Transmission Provider with an electrical design and wind turbine/plant models that will be used for subsequent interconnection studies as described in Order 2003-A. The process described here will be a requirement for FERC-regulated transmission providers to adopt.

What impact will the Grid Code have on wind generator manufacturers?
Turbine manufacturers will focus on two areas of the Grid Code. First, the technical specifications for performance will allow manufacturers to plan the design of turbines with greater certainty. The low voltage ride-through standard proposed is the same as the anticipated standard for interconnection that will become common in Europe.

Second, the proposal seeks to require that Transmission Providers and wind generator manufacturers participate in a formal process for developing, updating and improving the engineering models and turbine specifications used for modeling the wind plant interconnection. Given the rapid pace of wind turbine product development and the key role these models play in determining interconnection costs and requirements, it is imperative that these models reflect current generator technologies accurately and be updated and validated in a timely manner as new turbine product development occurs. AWEA believes it should be a requirement of the interconnection tariffs that Transmission Providers participate along with wind turbine manufacturers in a reasonable, formal process for achieving this result.

What allowance is made for planned projects and inventories of equipment?
By the time the Commission finalizes these equipment standards, most projects that will seek interconnection in the months immediately following the order will have already made commitments for their turbines and will have planned their projects without reference to these new standards. Accordingly, in order for the industry to implement these standards without substantial project disruption or “stranded” equipment, AWEA proposes that the physical standards proposed herein take effect for interconnection requests submitted to a Transmission Provider on the latter of: 1) final approval of the Transmission Provider’s interconnection tariff incorporating these standards; or 2) six (6) months following the Commission’s final rule.

What effect does the Grid Code Filing have on existing wind farms?
There is no mechanism to apply the proposed standards to existing wind projects.


Wind Energy & Energy Policy | AWEA Home Page

© 2004 by the American Wind Energy Association.
May be freely distributed provided this notice is included.
All other rights reserved.